Heckfield House Spa and Hotel, ‘The Bothy’ project was taken over by Brymor contactors after lying unfinished for over a year. The project was a spa, health, beauty and fitness facility for hotel users and members.

We were asked to put together a suitable designed scaffold to encapsulate the building with a scaffold temporary roof, specifically designed to allow all external works to proceed with minimum interference to the scaffold.

The design was carried out by 9design’s Wayne Heaver with input from both Liddiard managers and Brymor senior management.

The initial package was placed for external scaffolds with some minor internal works, as the project progressed the scaffold requirement intensified too the basement, lower ground floor, ground floor and swimming pool with plant room. Terrace areas, planters and sunken garden were re-designed to allow works to proceed.

Get a Free Quote

Contact us today by telephone, email or use our free contact form on the contact page. Our office is open from 7am-5.00pm, please call us on 01730 710578 or email us at info@liddscaff.com and a friendly team member will be more than happy to help.